A Conceptual Framework for Application of Performance Measurement as an Early Warning System in Projects, an Analysis on the Case of the London Ambulance Service Project

Conference paper


Hajikazemi, S., Andersen, B and Krane, HP (2012). A Conceptual Framework for Application of Performance Measurement as an Early Warning System in Projects, an Analysis on the Case of the London Ambulance Service Project. PMI® Research and Education Conference. Limerick, Ireland 15 - 18 Jul 2012
AuthorsHajikazemi, S., Andersen, B and Krane, HP
TypeConference paper
Abstract

This study presents an overview of the concept of early warning signs in projects and explains how a performance measurement system can be
utilized as an early warning signal for avoiding failure. An analysis will be done on the published assessments of a project, the London Ambulance
Service, which failed to fulfill its goals. This analysis has been performed in order to illustrate the feasible problems pertaining to a real case and
its consequences. The rationale behind this selection is not to offer criticism relating to this specific project's performance but to learn
constructively from it and move towards a better practice. A statement has been made that, with application of a performance measurement
system in the project phase, chaos and perhaps total failure in the operational phase could have been prevented. Also, a conceptual performance
measurement system has been proposed, using the main problems in the project phase as a reference for addressing the dimensions of
performance to be measured, objects to be controlled, and the indicators. The overall aim of this paper is to increase understanding of the
concept of early warning signs in projects and offer a possible approach, which can assist project managers in taking timely preventive actions in
order to avoid undesired outcomes.

Keywordsperformance measurement; project failure; early warning signs; conceptual framework; London Ambulance Service
Year2012
Accepted author manuscript
License
Publication dates
Print15 Jul 2012
Publication process dates
Deposited06 Mar 2019
Accepted15 Jul 2012
Permalink -

https://openresearch.lsbu.ac.uk/item/87980

  • 95
    total views
  • 128
    total downloads
  • 1
    views this month
  • 4
    downloads this month

Export as

Related outputs

To be or not to be: why do transaction partners in construction industry avoid formulating agreements into contract documents?
Chen, Y., Wu, Y., Hajikazemi, S., Yao, H. and Ebohon, O. (2022). To be or not to be: why do transaction partners in construction industry avoid formulating agreements into contract documents? CIB WBC 2022. RMIT, Melborune, Australia 27 - 30 Jun 2022
Sexism and Project Studies: The Case of Construction and Engineering Organizations
Hajikazemi, S. and Locatelli, G. (2021). Sexism and Project Studies: The Case of Construction and Engineering Organizations. European Academy of Management. Montreal 16 - 18 Jun 2021
Making Tomorrow a More Resilient Place: On Black Swans in The Project-Based Firm
Hajikazemi, S. and Walton, A.J. (2020). Making Tomorrow a More Resilient Place: On Black Swans in The Project-Based Firm. European Academy of Management. Dublin 04 - 06 Dec 2020
Normalising deviance in construction project organizations: a case study on the collapse of Carillion
Hajikazemi, S., Aaltonen, K., Ahola, T., Aarseth, W. and Andersen, B. (2020). Normalising deviance in construction project organizations: a case study on the collapse of Carillion. Construction Management and Economics. https://doi.org/10.1080/01446193.2020.1804069
Normalization of deviance in the construction industry, a managerial perspective
Hajikazemi, S., Ahola, T, Aaltonen, K, Aarseth, W and Andersen, B (2019). Normalization of deviance in the construction industry, a managerial perspective. EURAM 2019: Exploring the future of management. Lisbon, Portugal 26 - 28 Jun 2019
Overcoming barriers against interaction on innovation capabilities within and between smes
Hajikazemi, S., Ekambaram, A, Røstad, CC and Henriksen, B (2018). Overcoming barriers against interaction on innovation capabilities within and between smes. Moon, Ilkyeong, Lee, Gyu M, Park, Jinwoo, Kiritsis, Dimitris and Cieminski, Gregor von (ed.) IFIP WG 5.7 International Conference. Seoul, Korea 26 - 30 Aug 2018 Springer. https://doi.org/10.1007/978-3-319-99704-9_28
Analyzing electrical installation labor productivity through work sampling
Hajikazemi, S., Andersen, B and Langlo, JA (2017). Analyzing electrical installation labor productivity through work sampling. International Journal of Productivity and Performance Management. 66 (4), pp. 539-553. https://doi.org/10.1108/IJPPM-06-2016-0122
Downfall in the Oil Price; Challenges and Opportunities for the Construction Industry
Hajikazemi, S., Olsson, N, Ekambaram, A, Andersen, B and Langlo, JA (2017). Downfall in the Oil Price; Challenges and Opportunities for the Construction Industry. 9th Nordic Conference on Construction Economics and Organization. Goteborg, Sweden 12 - 14 Jun 2017
Value Co-creation through Early Warning Signs in a Project Setting
Hajikazemi, S., Razmdoost, K and Smyth, H (2017). Value Co-creation through Early Warning Signs in a Project Setting. European Academy of Management (EURAM). Glasgow, Scotland 21 - 24 Jun 2017
The Black Swan – Knowing the Unknown in Projects
Hajikazemi, S., Ekambaram, A, Andersen, B and Zidane, YJ-T (2016). The Black Swan – Knowing the Unknown in Projects. Procedia - Social and Behavioral Sciences. 226, pp. 184-192. https://doi.org/10.1016/j.sbspro.2016.06.178
Remedies for Managing Bottlenecks and Time Thieves in Norwegian Construction Projects – Public vs Private Sector
Eik-Andresen, P, Landmark, AD, Hajikazemi, S., Johansen, A and Andersen, B (2016). Remedies for Managing Bottlenecks and Time Thieves in Norwegian Construction Projects – Public vs Private Sector. Procedia - Social and Behavioral Sciences. 226, pp. 343-350. https://doi.org/10.1016/j.sbspro.2016.06.197
Barriers against effective responses to early warning signs in projects
Hajikazemi, S., Andersen, B and Klakegg, OJ (2015). Barriers against effective responses to early warning signs in projects. International Journal of Project Management. 33 (5), pp. 1068-1083. https://doi.org/https://www.doi.org/10.1016/j.ijproman.2015.01.002
The Early Warning Procedure in an International Context
Hajikazemi, S., Andersen, B, Eleftheriadis, R and Capellan, A (2015). The Early Warning Procedure in an International Context. Procedia - Social and Behavioral Sciences. 194, pp. 85-95. https://doi.org/https://www.doi.org/10.1016/j.sbspro.2015.06.122
Detecting Early Warning Signs of Delays in Shipbuilding Projects
Hajikazemi, S., Arica, E, Semini, M, Andersen, B and Alfnes, E (2015). Detecting Early Warning Signs of Delays in Shipbuilding Projects. Advances in production management systems. Tokyo 07 - 09 Sep 2015
Efficiency of project health checks (PHCs) as an early warning system in practice: a case study in Norway telecommunication industry
Hajikazemi, S. and Andersen, B (2014). Efficiency of project health checks (PHCs) as an early warning system in practice: a case study in Norway telecommunication industry. International Journal of Managing Projects in Business. 7 (4), pp. 678-700. https://doi.org/10.1108/IJMPB-01-2014-0012
Identification of Early Warning Signs in Front-End Stage of Projects, an Aid to Effective Decision Making
Hajikazemi, S., Andersen, B and Krane, HP (2013). Identification of Early Warning Signs in Front-End Stage of Projects, an Aid to Effective Decision Making. Procedia - Social and Behavioral Sciences. 74, pp. 212-222. https://doi.org/https://www.doi.org/10.1016/j.sbspro.2013.03.011
Application of performance measurement as an early warning system
Hajikazemi, S. and Andersen, B (2013). Application of performance measurement as an early warning system. International Journal of Managing Projects in Business. 6 (4), pp. 714-738. https://doi.org/https://www.doi.org/10.1108/IJMPB-04-2012-0015
A Review on Possible Approaches for Detecting Early Warning Signs in Projects
Hajikazemi, S., Andersen, B and Krane, HP (2013). A Review on Possible Approaches for Detecting Early Warning Signs in Projects. Project Management Journal. 44 (5), pp. 55-69. https://doi.org/https://www.doi.org/10.1002/pmj.21360
Preliminary Investigation of Project Success Criteria in Norway
Hajikazemi, S., Hussein, B and Ramazany, S (2011). Preliminary Investigation of Project Success Criteria in Norway. The 6th IEEE International Conference on Intelligent Data Acquisition and Advanced Computing Systems: Technology and Applications. Prague 15 - 17 Sep 2011